Overview Back to top

Workload bars are shown on the Resource Scheduler and on My Work. They compare planned hours with available hours, per person per day, in hours (h) or as a percentage (%). Capacity schemes, holidays, leave and allocations are taken into account.

Two words are used throughout this page:

  • Capacity — the hours a person can work on a day. It comes from their capacity scheme, for example 8 hours Monday to Friday.
  • Workload — the hours planned for that person on that day, from their items and allocations.

With workload on, every day of every person on the Scheduler gets a small coloured bar. The bar compares the workload with the hours the person is available, after holidays and approved leave are taken off.

The workload bar under each day fills up as hours are planned. The label reads planned / available, for example 9/8h. Demo data.

In the Year - Monthly view there is one bar per month instead of one per day.

When would I use this?

Turn workload on when you plan or hand out work. You see at a glance who can take more and who has too much, before it becomes a problem.

Turning Workload On Back to top

  1. Open the Resource Scheduler.
  2. In the toolbar, set the Off / On switch next to Workload to On.
  3. Click the button next to the switch to open Choose Workload Mode. There you pick what the bars count (see View modes) and whether numbers show in hours (h) or as a percentage (%).

Set the switch to Off to hide the bars again.

What the Colours Mean Back to top

The percentage is the planned hours divided by the available hours of that day.

Colour Meaning
Light blue Up to 50% — plenty of free time.
Green Over 50%, up to 100% — well loaded, within capacity.
Orange Over 100%, up to 120% — slightly overbooked.
Red Over 120% — overbooked, needs action.
Striped blue A full day of approved leave.
Striped orange A public holiday. With a ⚠ sign, work is planned on the holiday.
Striped purple with ⚠ Conflict — work is planned on a full day of leave.
Grey A working day with nothing planned.

Weekends and other non-working days have no bar.

Workload Basis: Live or Planned Back to top

An admin chooses the Workload basis for the whole account in Settings › Workload. It decides how an item's hours are spread over days. It drives the Scheduler and the forecast reports.

First, three words about item hours:

  • Original estimate — the total hours planned for an item.
  • Logged time — the hours people have recorded on the item so far.
  • Remaining estimate — the original estimate minus all logged time. It never goes below zero.
Basis How hours are spread Use it when
Planned workload (default for new accounts) Each item's hours are spread evenly over all of its dates, past days included. The admin also picks the Estimate source: Original estimate (default) or Remaining estimate. Your team does not log time regularly, or you plan from estimates only.
Live workload The remaining estimate is spread from today to the item's end date. It shrinks as people log time. Past days show a dash. Your team logs time regularly and you want the plan to follow the work that is left.
Settings › Workload: the workload basis, the estimate source for Planned workload, and how shared items are counted.

The basis also drives the Resource Utilization Forecast and Board Resources Forecast reports. Both show the basis they used. Timesheet progress views and the Planned vs Actual report always compare against the original estimate.

Existing accounts. Accounts that were already using WorkHub before this setting was added stay on Live workload until an admin changes it.

View Modes Back to top

In Choose Workload Mode, each person picks what their own Scheduler shows. This changes only your view. Reports always follow the account's workload basis.

Basis Mode What the bar shows
Live Remaining Estimate (default) The work still left, from today on. Past days show a dash.
Availability The free hours left after the remaining work, from today on. Past days show a dash.
Original Estimate The planned hours spread over all of the item's dates. Logged time is ignored.
Planned Workload (default) The planned hours spread over all of the item's dates, past days included.
Availability The free hours left after that planned load.
Both Number of Items How many items the person has that day. No hours and no bar, only a count.
Which mode should I pick?

Use the default mode for everyday planning. Switch to Availability when you need to find who can take a new task. In Availability, a negative number such as -2h means the person is overbooked by that much.

Hours or percentage

The h and % buttons at the top of Choose Workload Mode change the label next to each bar.

Button Label Best for
h Planned and available hours, for example 6/8h. Knowing exactly how many hours are free.
% The load as a percentage, for example 75%. A quick scan across a week or month.

The colours are the same in both. The buttons are not shown in Number of Items mode.

Workload without time tracking

When an admin turns Time Tracking off in Settings › Timesheet Config, there is no logged time to subtract. Workload then uses each item's estimate, spread evenly over all of the item's dates.

  • The modes are Workload, Availability and Number of Items.
  • The app says Estimate wherever it said Original Estimate or Remaining Estimate.
  • The workload basis in Settings › Workload is shown but cannot be changed.
  • The Resource Utilization Forecast and Board Resources Forecast reports use the estimate too.

The saved workload basis and each person's own mode are kept. They come back when Time Tracking is turned on again.

How Workload Is Calculated Back to top

For each person and each day, WorkHub works out two numbers and divides them:

Load % = planned hours ÷ available hours × 100
  • Available hours = the person's capacity for that day, minus holidays and approved leave.
  • Planned hours = the hours of their items on that day, plus their allocations.

How an item's hours land on days

A board can give an item its hours in two ways. See Field Mapping for how to set them up.

  • Original Estimate (total hours) — the hours are spread evenly over the person's working days between the item's start and end date. For example, 16 hours over 4 working days is 4 hours a day. Holidays and full days of leave get no hours; the hours go to the other days.
  • Hours Per Day — the same hours on every working day of the item, for example 3 hours a day. Logged time does not reduce it.

Items with no hours add nothing to the workload.

Example — a slightly overbooked day

A person can work 8 hours a day. On Monday they have three items: 4h, 2h and 3h. That is 9 planned hours against 8 available: 9 ÷ 8 = 112.5%. The bar is orange.

How the remaining estimate works

When the workload counts remaining work, WorkHub subtracts logged time from the estimate:

  • Remaining = original estimate − all time logged on the item. All logged time counts, also time logged before the dates on screen.
  • Under Live workload, the remaining hours are spread over the working days from today to the item's end date.
  • Under Planned workload with the Remaining estimate source, they are spread over all of the item's working days.
  • If more time is logged than estimated, the remaining is 0. The item bar gets a red dashed border as a warning.
  • Items that use Hours Per Day keep their daily hours. Logged time does not reduce them.

Click an item bar to see its Original Estimate, Logged and Remaining hours. Click the Logged value to see every time entry on the item.

Holidays and Leave Back to top

Holidays and approved leave lower the available hours of a day. The workload bar adjusts by itself.

Day Available hours Bar
Regular working day The full hours of the capacity scheme, for example 8h. Normal colours.
Public holiday 0h Striped orange
Full day of leave 0h Striped blue
Half day of leave Half of the day, for example 8h → 4h. Normal colours against the lower hours.
Leave for a few hours The day minus the leave hours, for example 8h − 2h = 6h. Normal colours against the lower hours.
Weekend or other non-working day 0h No bar.

Only approved leave lowers the available hours.

Work planned on a day off

A ⚠ sign on a holiday or leave day means work is planned there and could not be moved to another day. This can happen with Hours Per Day items, which keep their hours on every day, and with items or allocations whose every day is a day off. Move the work to other dates or to another person.

Example — half day of leave

A person with 8 hours a day takes a half day of leave on Wednesday. They have 4 hours available. With 3 planned hours the load is 3 ÷ 4 = 75%, green. With 5 planned hours it is 5 ÷ 4 = 125%, red.

Items with Several Assignees Back to top

When an item has more than one assignee, the Per-Person Hour Distribution setting decides how its hours are counted.

Setting What happens Example
Enabled The hours are divided equally among the assignees. 8h item with 2 assignees → 4h each
Disabled Each assignee gets the full hours. 8h item with 2 assignees → 8h each

An admin sets the account default in Settings › Workload › Workload Defaults. A single board can use its own value in Board settings › Workload Settings: Use account default, Enabled or Disabled.

Tip

Enable it when assignees share the work. Disable it when each assignee does the full estimate on their own, for example reviewers.

Day Details Back to top

Click any workload bar to see the numbers behind it. The popup shows the person's planned and available hours for the period on screen, with the percentage. Below that is one line per day. If the person has allocations, the popup also shows how many of the hours are allocations.

Tips Back to top

  • To fix a red day, drag an item to another day, or drag it to another person's row to reassign it.
  • You can also make an item longer. Its hours are then spread over more days.
  • Use Availability mode to see exactly how many free hours each person has.
  • Keep estimates up to date on your boards. The bars are only as accurate as the estimates behind them.
  • Make sure each person has the right capacity scheme and holiday scheme. People without a scheme use the account default.
  • For longer periods, use the Resource Utilization Forecast report.

Need Help?

If you have questions or need assistance, our support team is here to help.